NY Route 5 - Main Street Reconstruction
Two-Week Schedule
The following information
summarizes the Contractor's anticipated work schedule and locations for the
next 2 weeks.
Week September 27
– October 2 (Schedule
is weather dependent)
Traffic flow is expected to
be slow from Route 98 to Colonial
Blvd. and
including Lewiston
Rd. and in
areas of miscellaneous lane closures , so all travelers should allow extra time
for their trips through the project area.
All motorists are advised
to obey traffic laws and not to block intersections.
- Monday, Sept.
27 – Paving Operations on Route 98 (Oak Street) at Route 5
(West Main Street) from
approx. 7A.M. till 12P.M. North and South bound traffic on Route
98 will be reduced to single lanes.
Traffic delays are to be expected.
Please, allow for additional time if traveling thru this area.
- Monday,
Sept. 27 – Route 63 (Ellicott
Street) between
Route 5 (West Main
Street) and Court
Street will be closed to all thru traffic for paving operations. This is expected to take place between 11 A.M. until 5P.M. All North and South bound traffic using
Route 63 will be directed to use Court Street as a detour. If at all possible avoid this area
because traffic delays are expected to severe.
- Tuesday,
Sept. 28 – Paving operations are expected to continue on side streets
along West Main
Street from
downtown to Lyons
Street. Short term closures will occur while
paving operations continue.
Preparation for paving from Lyons
Street to the
Project’s west limit will reduce traffic to a single lane of traffic
in each direction (East and West) along Route 5 (West Main
Street).
- Wednesday,
Sept. 29 – Mainline paving operations on Route 5 (West
Main Street) from Lyons
Street to the Project’s west
limit will occur from 6A.M. till
7P.M. Traffic will be reduced to single lanes
in both East and West bound directions.
Access to side streets and properties will be limited while paving
operations proceed thru. All
efforts will be made to limit delays, but there will be times when
property access will be restricted.
All access will be restored as is practical to run traffic over the
newly placed asphalt. This will
impact the intersection with Lewiston
Road.
- Thursday, Sept. 30 –
Paving operations on Lewiston Road (Route 63) from 7A.M. till 5P.M. Traffic will be reduce to a single lane
in both the North and South bound directions.
- Friday, Oct. 1 – Paving operations are
expected to continue on side streets along West Main
Street from Lyons
Street to Colonial
Boulevard. Short term closures on side streets will
occur while paving operations continue.